Application of fuzzy numbers to the estimation of an ongoing project’s completion time
A dynamic, interactive approach to the control of a project’s realization time is proposed. The
duration time of the project’s activities is assumed to depend on certain factors whose influence
may change in time. Based on the project’s history up to a certain moment, the change in influence
of these factors has been evaluated and estimates of the duration of activities which have not been
started yet are updated. The estimates of the duration time of the activities and project are expressed
in the form of fuzzy numbers. This allows us to keep a constant track of the risk of the project
not keeping the deadline and to be aware of which factors influence delays, thus where to act
in order to minimize the final delay while it is not yet too late – in the course of the project’s realization,
as early as possible.